Phase 1: the dismantling of the tent
During the closed season (January 1st until February 10) of the site of the Hermione, work continues in preparation for the installation of the boat-locks and the moving of the frigate to the Napoleon III drydock in July.
Preparing the launch: the sequel ...
Phase 2 : The shoring for the launch!
2012 was a pivotal year for the Hermione! After dismantling the tent that covered the Hermione in the double drydock where she was constructed, the ship was cleared of all its scaffolding and showed itself to the visitors, adorned with its original colors.
************************************************************
Une hermione à l'air libre !
COMMENTS:
- Découvrez la pose du POD tribord, moteur à propulsion pesant 1,5t, installé à l'arrière de la frégate. Un compromis entre historicité et navigabilité, mais nécessaire aujourd'hui pour assurer la maniabilité du navire dans un port.
- Arrêtez de rager inutilement ! Ces POD sont OBLIGATOIRES pour naviguer avec l’Hermione, tout simplement parce qu’il est aujourd’hui totalement interdit de manœuvrer à la voile dans un port. Les POD serviront uniquement dans ce cas de figure. Des tas de concessions et de compromis ont était fait sur ce projet mais c’est toujours pour que le navire puis « vivre ». Et heureusement, sinon il n’aurait jamais pu prendre la mer. L’essentiel est bien là et c’est ce que compte.
These works will follow each other and will take approximately 1 ½ months.
Click here to see the VIDEO!
No comments:
Post a Comment